The US Navy has successfully completed testing of the Next Generation Jammer Low Band (NGJ-LB) program at the Naval Air Station Patuxent River, Maryland, with limited staffing while remaining on schedule despite significant COVID-19 restrictions.
To continue reading the rest of this article, please log in.
Create free account to get unlimited news articles and more!
Airborne Electronic Attack Systems Program Office (PMA-234) NGJ-LB team was ready to begin its final demonstration of existing technologies (DET) testing when COVID-19 restrictions were put into place.
After a quick reassessment, the team held teleconference meetings with Naval Test Wing Atlantic Chief Flight Surgeon, government, and contractor participants to gain consensus on quarantine and test execution requirements.
They made the required Center for Disease Control and NAVAIR readjustments and were still able to complete testing with two contractors’ prototype pods at both Air Combat Environmental Test and Evaluation Facility (ACETEF) and the Facility for Antenna and RCS Measurement (FARM) in less than two months.
Dan Doster, NGJ-LB assistant program manager for test and evaluation, explained, "Our start was delayed two and a half weeks to comply with a request from one of the contractors to delay testing in order to self-quarantine their personnel.
"This started a cascading effect that resulted in our test execution days being reduced from 15 to 10 days for the ACETEF test events for each contractor, but the team still managed to stay on schedule."
Other constraints included a 50 per cent reduction in staff at the FARM and ACETEF control rooms.
Greg Brannon, FARM lead, expanded on this, saying, "If that one person or anyone on the team became infected and caused the rest of the team to be quarantined, or if the FARM had to be shut down for disinfecting, testing would have come to a halt, and it would have been very difficult, perhaps impossible, to recover."
Brannon said the team took mitigations to prevent that “doomsday” scenario very seriously.
"We were very cautious about who people came in contact with on and off the job and performed daily health screenings for every person that entered the FARM. The mitigations may have been overboard, but they worked," Brannon said.
Despite the restrictions, the many teams involved were able to stay on task. The NGJ-LB test team was comprised of PMA-234 Program Office; L3Harris; Northrop Grumman Corporation; FARM; ACETEF; Air Test and Evaluation Squadron (VX) 23; Johns Hopkins University Applied Physics Laboratory; Naval Air Warfare Center-Weapons Division; PMA-234’s Jammer Technique Optimization (JATO); and Southern Maryland Crane Rental personnel.
PMA-234 program manager Michael Orr, who oversees the NGJ-LB program, said, "The collaboration efforts of these organisations that spans across the country, have been tremendous. This was an incredible feat and I am extremely proud of the government and industry teams’ ability to adapt and overcome. They all stepped up to make the necessary adjustments needed to complete these simultaneous test events and keep the NGJ-LB program on track to meet our next milestone."
The 22-month DET contract, awarded to L3Harris and Northrop Grumman Corporation, has been a collaborative effort with the industry partners to assess technical maturity and will conclude later this summer.
The US Navy is currently in source selection to choose a prime contractor to develop the NGJ-LB Capability Block 1 tactical jamming operational prototypes with a contract award anticipated this fall.
NGJ-LB is part of a larger NGJ weapon system that will augment, and ultimately replace the legacy ALQ-99 Tactical Jamming System currently used for airborne electronic attack on the EA-18G Growler aircraft.